Stardust Power cuts Oklahoma lithium refinery costs by $200 million
FREE Breaking News Alerts from StreetInsider.com!
StreetInsider.com Top Tickers, 6/30/2026
- S&P 500, Nasdaq post best quarter since 2020 despite Iran war
- Dollar pushes higher, yen sinks to 40-year low
- NVIDIA stock gains as SemiAnalysis sees H2 data center revenue 20% above consensus
- Citi says bearish flows are building in Nasdaq and S&P 500
- Patrick and LCI Industries to merge in all-stock deal
- Mizuho says ignore Apple noise, flags key catalyst for Micron and memory in H2
- EchoStar Prepares Dish DBS Bankruptcy Filing as Soon as Tuesday - WSJ
- Strategy stock jumps 7% as firm shifts to active capital management
- New leader board: Citi refreshes AI compute semiconductor picks
- Honeywell completes aerospace spin-off, splits into 3 companies
Stardust Power Completes Front End Loading 3 Report (FEL 3) for Its Oklahoma Lithium Refinery
September 9, 2025 7:30 AM EDTKey findings from the FEL 3 report include:
Phase 1 Capacity: 25,000 metric tons per annum of battery-grade lithium, expandable to 50,000 metric tons per annum in Phase 2, one of the largest planned refineries in the U.S.Capital Expenditures: ~$500 million for Phase 1, nearly $200 million below prior disclosed estimates, with a 90% probability of achievement. This figure includes owners cost, contingency and escalation.Construction Timeline: ~24 months from start of major construction to mechanical... More